Part 26: Ready for the Roof Framing

(Introduction, Syllabus, 1.Prelims, 1-4Precon, 2. Excavation, 3.Foundation, 4.Framing, 5.Roof, 6.Close, 7.MEP, 8.Finish)

The availability of standard milled framing materials, structural connectors, and skilled carpenters makes traditional wood framing the obvious choice for most types of residential construction. Wood framing resources include print publications and online information common to an industry of contractors, subcontractors, and material suppliers.

Setting Main Ridge Support
In this example, the ridge beam column supports are built into the gable walls at each end of the open ceiling. The walls are framed so that the sloping top plate matches the height and slope of the roof rafters.
Framing Phase – Insitebuilders
When floor space is limited, the walls are fabricated on the lower level and lifted with a portable material hoist that can be rented from most equipment rental companies, see www.genielift.com for specifications and information.
Framing Phase – Insitebuilders
The gable walls are set to vertical and stabilized with braces or framed into adjacent shear walls so that they remain ridged and in place while the main ridge and header beams are lifted into place.  

Final structural review
The structural integrity of a wood frame house is also easier to inspect and maintain. Most of the connectors and straps required for tie down can be installed after the floor and wall framing are complete. The size and placement of structural connectors varies with location and building loads.
Framing Phase – Insitebuilders
As a structural system, construction began with the installation of securely anchored pressure treated sills. The floor joists are then strapped to the sills and the foundation walls and the walls strapped to the joists. Interlocking top plates then tie the walls together to create a solid structural frame.

Once the walls and connectors are in place and inspected, exterior sheathing is installed with nails spaced according to code requirements. The sheathing further stabilizes the frame prior to beginning the roof framing.

Trusses Roof Framing
Most residential designers and contractors prefer placing concrete as a slab on grade and installing prefabricated roof trusses because they are much faster and cheaper than field framing a raised floor and open ceiling (see the Wood Council of America research results at www.wtca.org)
Framing Phase – Insitebuilders
  • Prefabricated trusses are economical for large floorplans
  • Less skilled labor required
  • Roof components are computer engineered
  • Simple and fast to erect with a placement plan
  • Quality controlled manufacturing reduces waste
  • On center spacing maximized to reduce materials
  • Long clear spans reducing interior bearing walls
  • Saving in roof labor and material mean less energy consumption
  • Reduced man hours, lower risk, overhead and worker insurance
Conventional Roof Framing
A conventionally framed roof is assembled in the field using off-the-shelf materials. The key advantages are found with smaller houses where reduced labor and faster production have less of an impact and are not a primary consideration (Note that predesign requires careful detailing and coordination with mechanical, electrical and plumbing systems).
Framing Phase – Insitebuilders
  • Best for smaller, custom homes with open spaces and ceilings
  • Framing materials are readily available from lumber suppliers
  • Open rooms and variable ceilings
  • Custom design features like clerestories and gables
  • Open interior sight lines
  • Greater square footage efficiency under the roof
  • Upper volume of house available for special features like lofts
  • Field control of framing details to simplify roof lines
  • Traditional style and design details for interior and exterior

(To be continued…)

---------------------------

 The material presented in this series has been taken from our book, “How a House is Built: With 3D Construction Models” The book includes annotated illustrations, captioned text, videos, models, and the 2D Preliminaries. 